Project progress

Confirmed milestones and next objectives.

Key information on the delivery of the 56 MW / 168 MWh battery energy storage facility in Raseiniai.

2025 Q1Grid connection
01

Letter of intent signed with Litgrid

The agreement established the principal terms for connecting the project to the transmission grid.

2025 Q2Development permit
02

VERT issued the energy storage development permit

Lithuania’s National Energy Regulatory Council issued the development permit (resolution No O3E-473).

2025 Q3APVA
03

Funding agreement signed with APVA

The project was awarded financing from the European Union Modernisation Fund under a measure administered by APVA.

2026 Q1Building permit
04

Construction permit obtained

The construction authorisation required to move the project into its delivery phase was issued.

2026 Q2Construction start
05

Construction of the Raseiniai storage facility commenced

Construction began at the project site at 37B Jurbarko Street in Raseiniai.

2026 Q3Equipment delivery
06

Critical equipment delivered to site

Battery modules, power conversion systems and other essential energy storage equipment arrived on site.

Q4 2026Planned
07

Construction completion

The principal construction and system preparation works are scheduled for completion.

H1 2027Planned
08

Generation permit

The generation permit is planned after testing and grid connection procedures are completed.